Optimasi Penjadwalan Proyek Kontruksi Dengan Metode Critital Path Method (CPM) dan Presedence Diagram Method (PDM) (Studi Kasus : PT. Samara Sentosa)

Aji, Nuke Maheswara (2025) Optimasi Penjadwalan Proyek Kontruksi Dengan Metode Critital Path Method (CPM) dan Presedence Diagram Method (PDM) (Studi Kasus : PT. Samara Sentosa). SiTekIn Jurnal Sains, Teknogi, dan Industri, 22 (2). ISSN 2721-2041

[thumbnail of 1 file judul_250027_21416226201002_Nuke Maheswara Aji.pdf] Text
1 file judul_250027_21416226201002_Nuke Maheswara Aji.pdf

Download (909kB)
[thumbnail of 2 file daftar isi_250027_21416226201002_Nuke Maheswara Aji.pdf] Text
2 file daftar isi_250027_21416226201002_Nuke Maheswara Aji.pdf

Download (398kB)
[thumbnail of 3 artikel_250027_21416226201002_Nuke Maheswara Aji.pdf] Text
3 artikel_250027_21416226201002_Nuke Maheswara Aji.pdf
Restricted to Registered users only

Download (932kB)
[thumbnail of 4 lampiran_250027_21416226201002_Nuke Maheswara Aji.pdf] Text
4 lampiran_250027_21416226201002_Nuke Maheswara Aji.pdf
Restricted to Registered users only

Download (748kB)

Abstract

Delays in construction projects often occur due to suboptimal scheduling, which results in increased costs and decreased efficiency. PT Samara Insan Sentosa faces a similar problem, where the planned project duration does not match the realization in the field. This study aims to optimize project scheduling using the Critical Path Method (CPM) and Precedence Diagram Method (PDM). The research methods used include secondary data analysis, interviews, and scheduling calculations with both methods. The results of the study show that CPM and PDM can identify critical paths and optimize project completion duration. A comparison of the two methods shows that PDM is more flexible than CPM, with a shorter project completion duration. Implementation of the PDM method can reduce project completion time without sacrificing the quality of work. The conclusion of this study is that scheduling optimization using the right method can increase project efficiency and reduce the risk of delays. The impact of this study can help companies improve the effectiveness of project management.

Keywords: Project scheduling, Critical Path Method (CPM), Precedence Diagram Method (PDM), critical path, optimization.

Item Type: Article
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Divisions: Faculty of Engineering, Science and Mathematics > School of Engineering Sciences
Depositing User: Pustakawan UBP Karawang
Date Deposited: 07 Apr 2026 08:52
Last Modified: 07 Apr 2026 08:52
URI: http://repository.ubpkarawang.ac.id/id/eprint/6162

Actions (login required)

View Item
View Item